All structural work was completed in August 2016. The four classrooms were finally handed over to the School Administration, School Management Committee and the Parent Teacher Association on 6th September 2016. Standard 7 and 8 pupils occupied the Classrooms (the 2016-2017 school year started on 5th September). This report provides a final update on the activities that were done with the financial support received from the Ellen Jane Rihoy Trust.