Plaza House, the Grade A headquarter office centrepiece of the Admiral Park development, continues to take shape.
We are main contractor for the 6-storey 60% pre-let office block, including 67,000 sq ft of open plan office space and an extended multi-storey car park.
Currently on site the steel frame is nearing completion, with the reinforced concrete floor slabs now being poured.
Ground floor tanking and formation of the lift pits and switch room substructure is underway, together with first fix mechanical and electrical containment to the central concrete core.Site Overview – Steel frame nearing completion Steel frame erection to ‘Block C’ nearing completion Steel frame erection to South ‘Block C’ nearing completion 1st floor temporary protection works to commence shortly Concrete complete to 1st floor ‘Block B’ Concrete complete to 2nd floor ‘Block A’, materials loaded out ahead M&E 1st fix Reinforcement complete to 2nd floor ‘Block B’ Concrete complete to 3rd floor ‘Block A’ and reinforcement complete to ‘Block B’ Comflor deck complete, and mesh complete to 3rd floor ‘Block B’ 1st fix containment and cabling in progress to core Ground floor slab prep and blockwork sleeper walls in progress to East Formation to switch room substructure nearing completion Tanking nearing completion to East lift pits MSCP site clear ahead of erection commencement next week.